Avent Ferry Road Realignment Project [Update]

Jan 05, 2022 11:17AM ● By Chris Hendricks

The realignment uses Pine Street to connect Avent Ferry Road with Stinson Avenue, reducing downtown congestion and serving as another access to the UNC Rex Holly Springs Hospital.

Location:

Avent Ferry Road, Pine Street

Estimated construction start:

Late 2022

Completed

  • Survey
  • Traffic analysis
  • Preliminary roadway alignment

Under Way

  • Design
  • Environmental permits & studies 
  • Private utility design

Estimated construction start:

Fall 2022

Public engagement:

Next steps: 

  • Right-of-way acquisition in 2022

Key partners:

NCDOT, Capital Area Metropolitan Organization, Duke Energy

Contact:

Utilities and Infrastructure Services: (919) 577-3150